Sequential test
A flood risk assessment is required for most proposed developments that are within a designated flood zone.
A sequential test may be required as part of a flood risk assessment. It compares the site for a proposed development with other available sites to determine which has the lowest flood risk.
A sequential test is required if:
- The development is in flood zone 2 or 3, AND
- A sequential test has not already been done for a development of the type proposed on the proposed site.
A sequential test is not required if:
- The development is a ‘minor development’ OR
- The development involves a change of use, unless it is a caravan, camping chalet, mobile home or park home site OR
- It is a development in flood zone 1, unless there are flooding issues in the area of the development.
The sequential test must conclude whether any of the alternative sites that have been identified have a lower risk of flooding than the proposed site. It should be submitted along with the flood risk assessment and the planning application to the local planning authority.
If the sequential test shows that it is not possible to use an alternative site, it may be necessary to undertake an exception test. This shows how flood risk will be managed on the proposed site and demonstrates that the sustainability benefits of the development to the community outweigh the flood risk.
For more information see: https://www.gov.uk/guidance/flood-risk-assessment-the-sequential-test-for-applicants
[edit] Related articles on Designing Buildings Wiki
- BREEAM Flood risk management.
- BREEAM Surface water run-off.
- Design flood event.
- Design flood level.
- Flood and Water Management Act.
- Flood defences
- Flood plain
- Flood risk
- Flood risk assessment.
- Flood risk management plan
- Flood zone
- Flood.
- Minor development.
- Planning for floods.
- Property flood resilience
- Sustainable urban drainage systems.
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.